Sponne School - Educational Facility

About the project

Principle Contractor: Steele & Bray Construction
Systems Covered: Hot & Cold Services, above ground drainage, gas, heating and ventilation. A new science block extension was constructed, our works included installing gas fired boiler, pressurisation unit, pump and controls installed in the new plant room to feed radiators and hybridventilation units in the new extension. The laboratories have hybrid ventilation units in the ceiling that are controlled by a controller on the wall. The Hybrid ventilation units have their own central control panel in the plant room and are interlocked with the gas solenoid valves in each laboratory.


Our works comprised of:

  • Installation of plant equipment
  • Installation of H&C, gas & AGD pipework, valves and lagging
  • Installation of new control panel
  • Installation of ducting and ventilation units
  • Testing and commissioning